      Is there a way to have Saturdays and Sundays to be treated as any other day? I tried everything at the calendar level. I can create a new custom calendar, but then:
      1. Each time I click back on “Calendar”, it shows the default calendar. I see my custom calendar in the list, but where does it says which calendar is applied?
      2. Whatever I do at the calender level, if I create a 2-day task starting on a Friday, it shows the task extended up to the next Monday (it treats Saturday and Sunday as non-working days).
      Thanks if you can help.

    • #9552
      Project_LibreProject_Libre
      Keymaster

      Yes both in the Desktop and Cloud versions….. create a new calendar and highlight Saturday and Sunday… with each select “Working Days” not default… then save the calendar. You can apply the Calendars at the Project, Task and Resource…..

    • #9553
      Project_LibreProject_Libre
      Keymaster

      Yes both in the Desktop and Cloud versions….. create a new calendar and highlight Saturday and Sunday… with each select “Working Days” not default… then save the calendar. You can apply the Calendars at the Project, Task and Resource…..